Construction continues. In this update, the basement and ground floor are completed.
June 4, 2016, before and after a big pour. The basement is being completed with pouring of the basement floors and walls.
|
Before: Rebar and forms for pouring concrete walls visible, left and top left (6/4/2016) |
|
After: Concrete poured to form a basement floor, right (6/4/2016) |
June 30 and July 1, moving upward:
|
Pouring a basement floor/ceiling above the lowest basement floor, left; erecting scaffolds to support the ground level floor, right (6/30/2016) |
|
After the latest pour, erecting more scaffolding to support the ceiling of the basement and the ground level floor, left and right (7/1/2016) |
|
Lunch break (7/1/2016) |
July 18, 2016:
|
Starting the big pour of the basement ceiling/ground floor (7/18/2016) |
July 20, 2016:
|
Ground floor, poured and curing (7/20/2016) |
So, after more than 8 months of digging downward and building upward, the future 35-story tower has reached the ground floor.